Insights and KPIs
The analytics dashboard — KPI cards, utilization and conflict trends, request-status history, and the bottlenecks and dependency chains that constrain the plan.
Insights (“Conflicts and utilization analytics”) is the health check for your operation: how much is scheduled, how well resources are used, and where plans collide — over a period you choose.
Filters
Two selectors drive the tabs:
- Date range — presets from “Last 6 months” to “Next 12 months”, including the combined “Last 6 / next 12 mo” view for planning across the present.
- Bucket — Weekly, Monthly, Quarterly, or Yearly aggregation for the trend charts.
The dependency chains on the Bottlenecks tab are the one exception. The date range selects which chains appear. The bucket does not apply to them.
Overview
KPI cards summarize the period at a glance:
- Total requests, Scheduled, Unscheduled — the state of the backlog.
- Conflicts — how many placements currently violate the model.
- {Type} utilization — one card per active resource type, so Mill utilization and People utilization sit alongside a card for every type you defined yourself (Resource types). Aggregate usage against configured capacity.
Below the cards, a Request status trend chart puts the backlog in motion (New, In progress, Done, Deferred, Canceled).
Utilization
One {Type} utilization trend chart per active resource type — Mill utilization trend, People utilization trend, Car utilization trend — shows how usage develops across the buckets you selected. Add a resource type and its chart appears here; deactivate one and it disappears. “No capacity configured for this period.” means exactly that: utilization is a ratio, and it needs configured capacity (working hours, availability) to be meaningful — see Scheduling and availability.
Conflicts
The conflicts tab lists every current conflict as a card, each labeled by kind — Scheduling Overlap, Capacity Exceeded, Capability Mismatch, Load Exceeded, Below Minimum Duration, Before Earliest Start, After Latest End, Size Mismatch, Dependency Violation — with the affected schedule and a link to the other request involved where relevant (“View other request”). The summary line keeps score: “No conflicts detected. All scheduled requests meet their requirements.” is the state to aim for. Above the list, the Conflict trend chart stacks the period’s conflicts by category — Overbooking, Criteria mismatch, Resource unavailable, Outside availability, Missing resource, and Sequence violation.
What each kind means and how to resolve it is covered in Understanding conflicts and the hands-on guide Find and resolve conflicts.
Bottlenecks
The bottlenecks tab answers a different question from the other three: not how the period trends, but what constrains the plan right now.
Two rankings sit at the top: Most overloaded stations and Most overloaded assets. Each lists the resources booked past their capacity, worst first, with the hours of overspill and the peak day as a percentage.
The split matches the rest of the app. A station has a fixed location and goes on a floorplan; an asset moves, and availability rather than position is how it gets planned (Stations, Assets). Ranked together, one busy class fills every place in the list and hides the other.
Each ranking has its own resource type selector. Keep it on “All stations” or “All assets” to see the class as a whole, or choose one type to see only mills, or only tools. People are assets, so they compete with your other assets for places in that list — select the type to look at one on its own.
The ranking is measured per day, whatever period you select. Overbooking is a spike: a machine slammed on nine days of a month and idle for the rest averages out to something comfortable, and a monthly figure hides exactly the days that hurt. An empty list means nothing was overbooked, which is the healthy state rather than missing data.
Below it, Dependency chains shows one row for each chain of linked open work. Each row shows where the chain starts and ends, its earliest deadline, and its Slack.
Slack is the time between the earliest finish of the chain and its deadline. A chain that misses its deadline shows a Late by badge. The chains with the least slack are at the top.
Select a chain to see its requests. Each request shows its earliest and latest dates and its Float. Zero float carries a Critical badge. Select a request to open it.
A chain appears when its dates overlap the date range. The computation itself always uses the whole chain. Finished work and requests with no dependencies do not appear. See Dependencies and the critical path.
Insights vs the board
The Utilization board is where you act; Insights is where you assess. Use Insights to spot the pattern — a chronically overbooked machine, a quarter with rising conflicts — then jump to the board to fix the instances.